San Diego Demolition Permit Requirements

Official San Diego demolition rules, checked against the city's own pages, plus 172 demolition permits issued in the last 12 months.

By the Home Permit Guide Editorial Team Last checked 3 official sources

Reviewed by Ken Pergeson, Permit Expediter & Code Compliance Consultant, Ventura County, CA ·

Short Answer

Yes, full removal

The City of San Diego requires a Demolition/Removal Permit from Development Services to completely demolish or remove any structure. Demolishing only part of a structure does not use this permit; partial demolition needs a Building Permit instead. Open plumbing and sewer lines must be capped in an approved manner either way, and no separate permit is needed to cap the sewer.

Source: City of San Diego: Demolition Permit (linked under Sources below)

San Diego Demolition Permits at a Glance

Demolition permits, last 12 months
172
Median application to issue
57 days
Slowest quarter took at least
242 days
Whole-building demolitions
69

Of the 8 cities we track for demolition, San Diego ranks 5 of 8 by median wait. The median declared job value on these permits was $62,296.

Who Can Apply and Do the Work

Applications are filed online as a standalone permit through the Development Services Application Portal, with the Demolition Removal Questionnaire, the San Diego Regional Hazardous Materials Questionnaire (HM-9171), the Waste Management Form for Construction and Demolition Debris (ES-008) and the Project Contacts form (DS-345). Owners doing the work themselves add the Owner-Builder Verification, DS-3042.

What You Need Before the Permit Is Issued

  • Historic review if the site has a designated historic resource, is in a designated historic district, or contains a structure 45 years old or older (Information Bulletins 580 and 581).
  • The Waste Management Form for construction and demolition debris.
  • The Regional Hazardous Materials Questionnaire.
  • PDF uploads that meet the City's file requirements, checked with its Scout validation tool.

What Else to Know in San Diego

Fees follow Information Bulletin 501, the fee schedule for construction permits. An issued Demolition/Removal Permit can be extended with form DS-117.

San Diego Demolition Permit Fees

San Diego does not publish a flat demolition fee we could verify, so we don't quote one. The fee is set when you apply. For scale, the median declared value of demolition work on recent permits was $62,296.

What San Diego's Demolition Permit Data Shows

Type of demolitionPermitsShare
Whole building6940%
Garage, shed or other accessory structure9555%
Partial demolition85%

Demolition Permits Issued per Month

12 Nov 22 Dec 11 Jan 11 Feb 19 Mar 21 Apr 22 May 14 Jun 11 Jul 9 Aug 14 Sep 5 Oct
San Diego demolition permits issued per month, Nov 2025 to Oct 2026. Lighter bar = current month to date.

Types are classified from each permit's description. Approvals whose scope mentions demolition, including pools, garages and other accessory structures. Data from City of San Diego Development Permits (Set 2), October 30, 2025 to October 30, 2026.

Where Demolitions Are Happening

ZIP codePermits (12 mo)
9203712
9212911
921268
921317
921156
921106

Recent Demolition Permits

IssuedWork as described by the city
2026-10-23For demolition of the 1-car garage and construction of a new detached 2-car garage on the existing 1-story SFD
2026-10-23Demolition Removal permit for the proposed demolition of a 4ft deep pool in the rear yard of an existing SFR p
2026-10-14For the proposed demolition of an 8' depth pool in the rear yard of an existing SDU.
2026-10-08Proposed Demolition of a 346-SF existing masonry building. (3447 5th).
2026-10-05For the demolition of an existing deck attached to an existing SFR and replacement with a smaller deck and sta
2026-09-28Proposed demolition of a 5-FT in depth pool in the rear yard for an existing SDU.

How to Get a Demolition Permit in San Diego

  1. Check historic and landmark status first. It is the step most likely to add weeks or months.
  2. Line up the prerequisites listed above, starting with the asbestos survey, pest control and utility disconnections.
  3. Hire a contractor licensed for demolition where San Diego requires one, and sign a written contract.
  4. Apply, post any required notice, and wait out the notice period before work begins.
  5. Pass the final inspection and keep the permit with your property records, especially if you plan to rebuild.

Frequently Asked Questions

Do I need a permit to demolish a house in San Diego?

The City of San Diego requires a Demolition/Removal Permit from Development Services to completely demolish or remove any structure. Demolishing only part of a structure does not use this permit; partial demolition needs a Building Permit instead. Open plumbing and sewer lines must be capped in an approved manner either way, and no separate permit is needed to cap the sewer.

How long does a demolition permit take in San Diego?

For the 172 demolition permits issued between October 30, 2025 and October 30, 2026 with both dates published, the median time from application to issue was 57 days, and a quarter took 242 days or longer, according to the city's open data.

How many demolition permits does San Diego issue?

172 in the 12 months to October 30, 2026. About 40% were for whole buildings, 55% for garages, sheds and other accessory structures, and 5% for partial demolitions, based on the permit descriptions.

Do I need a demolition permit to tear down part of my house in San Diego?

No. A Demolition/Removal Permit is only for complete demolition or removal of a structure; partial demolition is covered by a Building Permit.

Written and maintained by the Home Permit Guide Editorial Team

Last updated

Every rule on this page links to the official source it was checked against. Read our Editorial Policy.

Sources

Official sources checked on . Rules change; confirm with the department before you start work.

  1. City of San Diego: Demolition Permit (sandiego.gov)
  2. City of San Diego Information Bulletin 710: Building Demolition/Removal (sandiego.gov)
  3. City of San Diego Development Permits (Set 2) (data.sandiego.gov)