Austin, TX · ADU Permit

Austin ADU Permit Requirements

Official Austin ADU rules, checked against the city's own pages, plus 71 ADU permits issued in the last 12 months.

By the Home Permit Guide Editorial Team Last checked 3 official sources

Reviewed by Carlos Aldaba, CBO, Certified Building Official (ICC), Building Code & Permitting Consultant ·

Short Answer

Yes, building permit

Austin allows additional dwelling units on lots zoned SF-1, SF-2 or SF-3 of at least 5,750 square feet. Since HOME Phase 1 took effect on February 5, 2024, those lots can hold up to 3 units, with no primary or secondary unit distinction and no zoning separation minimum. Each unit needs a building permit through Residential Plan Review.

Source: City of Austin: Additional Dwelling Units (linked under Sources below)

Austin ADU Permits at a Glance

ADU permits, last 12 months
71
Median application to issue
224 days
Slowest quarter took at least
720 days
New detached ADUs
39

Of the 7 cities we track for ADUs, Austin ranks slowest by median wait.

Who Can Apply and Do the Work

Apply with the New Construction and Addition Building Permit application through Residential Plan Review. Plan review fees are invoiced and paid through the AB+C portal. Each unit needs its own unique address.

What You Need Before the Permit Is Issued

  • Confirm the lot is zoned SF-1, SF-2 or SF-3 and is at least 5,750 square feet.
  • Check deed restrictions yourself; the City does not enforce them.
  • Fire separation under IRC R302.1(1) still applies even though the zoning separation minimum is gone.
  • Request an address for each unit.

What Else to Know in Austin

HOME stands for Home Options for Families and Missing Middle Housing. Phase 1 replaced the old two-unit and ADU rules on single-family lots; read the City's HOME amendments page before designing.

Austin ADU Permit Costs

Austin does not publish a flat ADU permit fee; plan check and permit fees are calculated from the project valuation when you apply, so we don't quote one.

What Austin's ADU Permit Data Shows

Type of ADUPermitsShare
Conversion of a garage, basement or other existing space57%
New detached ADU3955%
Attached ADU1217%
Junior ADU00%
Not specified in the description1521%

ADU Permits Issued per Month

6 Nov 10 Dec 13 Jan 3 Feb 2 Mar 6 Apr 10 May 5 Jun 2 Jul 7 Aug 0 Sep 4 Oct
Austin ADU permits issued per month, Nov 2025 to Oct 2026. Lighter bar = current month to date.

Types are classified from each permit's description. Building permits whose description mentions an ADU or additional or accessory dwelling unit. Data from Austin Issued Construction Permits, October 30, 2025 to October 30, 2026.

Where ADUs Are Being Permitted

ZIP codePermits (12 mo)
7870416
7874411
787576
787025
787035
787525

Recent ADU Permits

IssuedWork as described by the city
2026-10-22*Green Building* New 2-story 4 bedroom 3.5 bathroom two-family (duplex) residence with attached garage covered
2026-10-15Building 2 2 Story SFR rear of main house with alley access - ADU / Garage
2026-10-12*Green Building* New 2-story 4 bedroom 3.5 bathroom two-family (duplex) residence with attached garage covered
2026-10-09Addition and remodel to existing 2-story residence part of two-unit use per the Home ordinance (originally bui
2026-08-13*Green Building* New 2-story 4 bedroom 3.5 bathroom two-family (duplex) residence with attached garage covered
2026-08-12*Green Building* New 2-story 4 bedroom 3.5 bathroom two-family (duplex) residence with attached garage covered

How to Get an ADU Permit in Austin

  1. Confirm what your lot allows. Zoning, existing unit count, hillside, fire and historic status decide which ADU types and how many you can add.
  2. Choose the program and plans. Decide between the State program and the Local program; they cannot be combined.
  3. Complete the prerequisites listed above before you file.
  4. File the building permit through PermitSF, over the counter or for in-house review.
  5. Build, pass inspections and get final sign-off before anyone moves in.

Frequently Asked Questions

Do I need a permit to build an ADU in Austin?

Austin allows additional dwelling units on lots zoned SF-1, SF-2 or SF-3 of at least 5,750 square feet. Since HOME Phase 1 took effect on February 5, 2024, those lots can hold up to 3 units, with no primary or secondary unit distinction and no zoning separation minimum. Each unit needs a building permit through Residential Plan Review.

How long does an ADU permit take in Austin?

For the 71 ADU permits issued between October 30, 2025 and October 30, 2026 with both dates published, the median time from application to issue was 224 days, and a quarter took 720 days or longer, according to the city's open data.

How many ADU permits does Austin issue?

71 in the 12 months to October 30, 2026. About 7% converted existing space such as a garage, 55% were new detached units, 17% were attached and 0% were junior ADUs, based on the permit descriptions.

How many units can I build on an Austin single-family lot?

Up to 3 units on lots zoned SF-1, SF-2 or SF-3 of at least 5,750 square feet, under HOME Phase 1, effective February 5, 2024.

Written and maintained by the Home Permit Guide Editorial Team

Last updated

Every rule on this page links to the official source it was checked against. Read our Editorial Policy.

Sources

Official sources checked on . Rules change; confirm with the department before you start work.

  1. City of Austin: Additional Dwelling Units (austintexas.gov)
  2. City of Austin: HOME Amendments (austintexas.gov)
  3. Austin Issued Construction Permits (data.austintexas.gov)