San Diego, CA · solar panel Permit

Do You Need a Solar Panel Permit in San Diego?

Official City of San Diego Development Services Department rules, checked against the city's own pages, plus 2,923 solar panel permits issued in the last 12 months.

By the Home Permit Guide Editorial Team Last checked 2 official sources

Reviewed by Ken Pergeson, Permit Expediter & Code Compliance Consultant, Ventura County, CA ·

Jump to Recent Permits

Short Answer

Yes

A Residential Rooftop-Mounted Solar PV Permit is required. For single-family, duplex and townhouse roofs designed to the IB 301 template, the "Photovoltaic - SB 379" permit is self-issued with no plan review if the system is 38.4 kW AC or less and needs no structural, fire or combination-permit review.

Source: City of San Diego: Residential Rooftop-Mounted Solar Photovoltaic (PV) Permit

San Diego Solar Panel Permits at a Glance

Permits, last 12 months
2,923
Issued, last 30 days
59
Median application to issue
0 days
Median declared job value
$335,979

Issuing office: City of San Diego Development Services Department. Rule last checked October 30, 2026.

Recent San Diego Solar Panel Permits

IssuedAddressWork
2026-10-28—pv solar roof mount and battery
2026-10-27—pv solar roof mount and battery
2026-10-27—ROOF MOUNTED SOLAR PV WITH BATTERY ESS
2026-10-27—installation of rooftop solar
2026-10-27—battery
2026-10-26—pv solar roof mount and battery
2026-10-26—Installation of PV with ESS
2026-10-23—Roof mounted PV & Energy Storage System installation
2026-10-23—pv solar roof mount + ESS+ MPU
2026-10-22—PV SOLAR ROOF MOUNT 19 PANELS / 7.79 kW DC & 1 ESS BATTERY & (N) Subpanel 125A

Addresses, work descriptions and contractor details as published by the city. San Diego's open-data feed does not publish the contractor for these permits. Owner names and personal phone numbers are never shown.

Permits Issued per Month

385 Nov 366 Dec 229 Jan 230 Feb 278 Mar 334 Apr 238 May 233 Jun 230 Jul 192 Aug 130 Sep 59 Oct
San Diego solar panel permits issued per month, Nov 2025 to Oct 2026. Lighter bar = current month to date.

Counts are approximate: we match permit types and descriptions to solar panel work. Data from City of San Diego Development Permits (Set 2), refreshed October 30, 2026.

What San Diego's Rules Say

  • Self-issued, no plan review: up to 38.4 kW AC on a single-family, duplex or townhouse roof built to the IB 301 template.
  • Can include a panel upgrade up to 320 amps and storage up to 38.4 kWh (each unit 20 kWh or less).
  • Structural roof changes need a Combination Building Permit instead.
  • Ground mounts over 5 feet high need a Building Permit.

San Diego Solar Panel Permit Fees

We have not verified San Diego's fee for this work from an official fee schedule yet, so we don't quote one. The City of San Diego Development Services Department sets the fee when you apply.

Busiest Areas for Solar Panel Permits

ZIP codePermits (12 mo)
92114203
92126165
92154163
92117140
92129129
92115126

How to Get a Solar Panel Permit in San Diego

  1. Confirm the rule for your exact job on the official page cited above. Size, height, structure and location (historic district, floodplain) can change the answer.
  2. Choose who applies. Many permits here must be pulled by a licensed contractor; ask any contractor to name the license they will use.
  3. Apply with the City of San Diego Development Services Department through the official department website.
  4. Schedule inspections as the permit requires, and keep the final approval with your house records.

Get 3 Local Quotes

Licensed San Diego pros for solar panel installation, who can pull the permit for you.

Get 3 Local Quotes

Free, no obligation. Licensed local pros for solar panel installation.

San Diego Solar Panel Contractors: Get Weekly Permit Lists

Contractors: get new permits for your trade and city every Monday. Join the waitlist.

Frequently Asked Questions

Do I need a solar panel permit in San Diego?

Yes. A Residential Rooftop-Mounted Solar PV Permit is required. For single-family, duplex and townhouse roofs designed to the IB 301 template, the "Photovoltaic - SB 379" permit is self-issued with no plan review if the system is 38.4 kW AC or less and needs no structural, fire or combination-permit review.

How many solar panel permits does San Diego issue?

San Diego issued 2,923 permits matching solar panel work between October 30, 2025 and October 30, 2026, about 244 a month. The busiest month was Nov 2025 with 385.

How much does a solar panel permit cost in San Diego?

We have not yet verified San Diego's fee for this work from an official fee schedule, so we do not quote one. The fee is set by the City of San Diego Development Services Department when you apply.

How long does it take to get a solar panel permit in San Diego?

Based on the city's records, the median time from application to issue for these permits was 0 days over the last 12 months.

Who issues solar panel permits in San Diego?

The City of San Diego Development Services Department.

More in this state: California Building Permits. Every city we cover is listed on Building Permits by City. Compare the same project in other cities from Permit Rules by Project Type. Plain-English explainers are collected in Homeowner Permit Guides.

Written and maintained by the Home Permit Guide Editorial Team

Last updated

Every rule on this page links to the official source it was checked against. Read our Editorial Policy.

Sources

Official sources checked on . Rules change; confirm with the department before you start work.

  1. City of San Diego: Residential Rooftop-Mounted Solar Photovoltaic (PV) Permit (linked above) (sandiego.gov)
  2. City of San Diego IB 301: Solar Photovoltaic Systems (sandiego.gov)