Check a Permit
Permit basics

Electrical Panel Upgrade Permit: Rules, Who Can Pull It and Permit Data

Replacing an electrical panel or increasing service size (say from 100 to 200 amps) always involves the utility connection and every circuit in the house. None of the cities we track treat it as exempt work, and several limit who can apply.

By the Home Permit Guide Editorial Team Updated Last checked 6 min read 6 official sources

Reviewed by Carlos Aldaba, CBO, Certified Building Official (ICC), Building Code & Permitting Consultant ·

Jump to the Answer
A two-story white house with black shutters and a front porch
Photo: Unsplash. Illustrative only; it does not show a specific permitted project.

Short Answer

Yes. A panel replacement or service upgrade needs an electrical permit in every city we checked, and in New York and New Orleans only a licensed electrician or licensed electrical contractor can get it. Chicago and Los Angeles both allow residential service up to 400 amps on a fast no-plans permit.

Key Takeaways

  • Chicago's Express Permit Program covers electrical work including new electrical service up to 400 amps.
  • LADBS issues express electrical permits for installations under 600 volts and up to 400 amps in existing residential buildings.
  • New Orleans requires an electrical permit for any electrical work except bulbs and fuses; only City Class "A" licensed electrical contractors can obtain it.
  • In New York City, the licensed electrician is the permit applicant for electrical work.
  • Chicago issued 3,360 panel or service permits in 12 months, the most among our cities.

Quick Facts

Chicago3,360 permits; median 0 days to issue. Express permit covers new service up to 400 amps
Austin1,624 permits; median 5 days to issue
New Orleans1,414 permits; median 10 days to issue. Fee: $40 + $3 per new circuit + $0.30 per amp
San Francisco129 permits; median 1 days to issue
New YorkLicensed electrician files the DOB electrical permit

From our city pages and each city's open permit data (refreshed October 30, 2026).

Why There Is No Exemption for Panel Work

Model codes and the cities we track carve out small electrical tasks from permits: Austin's exemption list, for example, allows replacing a breaker of the required capacity in the same location. Replacing the panel itself, adding a subpanel or upsizing the service goes well beyond that list. Service work affects the meter, the service entrance conductors and grounding, and it usually requires the utility to disconnect and reconnect power.

Step-by-Step: What to Do

  1. Get a load calculation or written reason for the size you are buying.
  2. Confirm the electrician's license and that they will pull the permit.
  3. Coordinate the utility disconnect and reconnect; the electrician usually books it.
  4. Pass the city's electrical inspection before the utility restores power where required.
  5. Keep the permit and final inspection for resale and insurance.

City Rules From Official Sources

Chicago

The Department of Buildings' Express Permit Program lists "performing electrical work, including new electrical service up to 400 amps" as eligible for residential remodeling permits without plan review. Our matched records show the scale: 3,360 permits; median 0 days to issue. Many Chicago descriptions say "electrical service" or give an amperage rather than "panel", so this count includes service upgrades as well as panel changes.

Los Angeles

LADBS lists electrical installations under 600 volts and up to 400 amps total load in existing residential buildings as express permits, with no plan check. It also lists EV charging installations up to 400 amps of service, including any needed service upgrade. Matching LA records were few (6), so we do not publish a figure for Los Angeles.

New Orleans

New Orleans requires an electrical permit to install, repair, replace or alter any electrical equipment except light bulbs and fuses, and only a contractor with a City Class "A" electrical license can obtain one. The published fee is a $40 application fee plus $3 per new circuit plus $0.30 per amp of service, so the service amperage portion of a 200-amp service is $60. The permit lapses after six months of inactivity.

New York City

NYC's Department of Buildings requires an electrical permit for electrical installation, alteration or repair, filed by a New York City licensed electrician. Our matched New York records for panel or service work were too few to publish.

Austin

Austin's exemption list covers only minor electrical work, such as replacing a breaker of the same capacity in the same location. Its Residential Change-Out permit, which covers HVAC and water heaters, excludes work involving circuits larger than 50 amps, so a panel or service change goes through a regular electrical permit. Austin still issued 1,624 permits; median 5 days to issue in our data.

How Many Panel and Service Permits Each City Issued

CityMatching permits (12 months)Median days, application to issue
Chicago3,3600
Austin1,6245
New Orleans1,41410
San Francisco1291

Permits issued 2025-10-30 through 2026-10-30, matched by keywords in each city's published permit descriptions. A permit can cover more than one job, and description wording varies by city, so treat counts as a floor rather than an exact total.

The median days figures show how fast a no-plans electrical permit can move: a few days in Austin and New Orleans. Chicago's records report a median of 0 days, meaning at least half of these permits were issued on the same day the application was recorded, which is typical of the Express Permit Program.

Panel Upgrades Tied to Other Projects

Panel upgrades often come with something else: a heat pump, an EV charger, solar or a kitchen remodel. Los Angeles folds a service upgrade for EV charging into the same express category, and solar permits in several cities depend on the rating of the existing panel. If your upgrade is part of a solar install, our guide to Solar Panel Permit Rules for Homeowners explains how panel size affects the solar permit path.

Questions to Ask the Electrician

  1. Will you pull the electrical permit, and under which license?
  2. What load calculation supports the new service size?
  3. Who arranges the utility disconnect and reconnect, and how long will the power be off?
  4. Is the permit fee in the quote?
  5. When is the inspection, and will you be there?

Where the law names a licensed electrician as the only permit applicant, a contractor who suggests skipping the permit is also telling you something about their license. More on this in Hiring a Licensed Contractor: Permit Rules That Depend on Licensing.

Building Departments in the Cities We Cover

Rules in this guide vary by jurisdiction. These are the official departments that issue residential permits in the 15 cities we track, with the city's open-data source for permit records. Each city page shows the rules for roofing, HVAC, solar, fence and deck work.

CityIssuing departmentPermit records
Chicago, ILChicago Department of BuildingsChicago Building Permits
New York, NYNYC Department of BuildingsDOB NOW: Build – Approved Permits
Los Angeles, CALos Angeles Department of Building and Safety (LADBS)LADBS Building Permits Issued 2020–Present
Austin, TXCity of Austin Development Services DepartmentAustin Issued Construction Permits
Seattle, WASeattle Department of Construction and Inspections (SDCI)Seattle Building Permits
Orlando, FLCity of Orlando Permitting ServicesOrlando Permit Applications
Philadelphia, PAPhiladelphia Department of Licenses and Inspections (L&I)Philadelphia L&I Permits (Carto)
Baltimore, MDBaltimore City Department of Housing & Community Development (DHCD)Open Baltimore: DHCD Permits
Nashville, TNMetro Nashville Department of Codes and Building SafetyMetro Nashville Building Permits Issued
Raleigh, NCCity of Raleigh Permit and Development ServicesRaleigh Building Permits
San Francisco, CASan Francisco Department of Building Inspection (DBI)DataSF: Building Permits
New Orleans, LANew Orleans Department of Safety and PermitsNOLA Permits
Pittsburgh, PAPittsburgh Department of Permits, Licenses, and Inspections (PLI)WPRDC: PLI Permits
Cincinnati, OHCincinnati Department of Buildings & InspectionsCincinnati Building Permits
Kansas City, MOKansas City, MO City Planning & Development DepartmentKCMO Permits (CPD)

Before relying on any rule, read the department's current page or call its permit desk. Model-code sections cited here (such as IRC R105) are adopted locally, often with amendments.

Frequently Asked Questions

Do I need a permit to upgrade from 100 to 200 amps?

Yes, in every city we checked. A service upgrade involves the utility connection and is outside the minor-work exemptions.

Can a homeowner pull an electrical permit in New Orleans?

The city says electrical permits can only be obtained by a contractor with a City Class "A" electrical license.

How much is an electrical permit in New Orleans?

The published fee is $40 plus $3 per new circuit plus $0.30 per amp of service.

Is a panel upgrade an express permit in Chicago?

Electrical work including new service up to 400 amps is eligible for the Express Permit Program, subject to its terms and conditions.

Written and maintained by the Home Permit Guide Editorial Team

Last updated

Every rule on this page links to the official source it was checked against. Read our Editorial Policy.

Sources

Official sources checked on . Rules change; confirm with the department before you start work.

  1. Chicago DOB: What Types of Work Are Eligible to Use the Express Permit Program? (chicago.gov)
  2. LADBS Information Bulletin P/GI 2026-003: Express Permits (No Plan Check Required) (dbs.lacity.gov)
  3. City of New Orleans: Electrical Permit (nola.gov)
  4. NYC DOB: Electrical Permit (nyc.gov)
  5. Austin DSD: Work Exempt from Building Permits (austintexas.gov)
  6. Austin Build + Connect Manual: Change Out Permit Qualifications (abc.austintexas.gov)