Do You Need a Permit for a Bathroom or Kitchen Remodel?

Cabinets, countertops and tile usually don't need a permit. Moving plumbing, adding circuits, replacing a tub or shower, or touching walls usually does. Most remodels contain some of both, which is why the honest answer depends on the scope.

By the Home Permit Guide Editorial Team Updated Last checked 6 min read 5 official sources

Reviewed by Carlos Aldaba, CBO, Certified Building Official (ICC), Building Code & Permitting Consultant ·

Jump to the Answer
A two-story white house with black shutters and a front porch
Photo: Unsplash. Illustrative only; it does not show a specific permitted project.

Short Answer

For finish work alone, usually no: Austin and Nashville exempt cabinets, countertops and similar finishes. Once a remodel replaces a tub or shower, moves or adds plumbing, adds electrical or changes walls, it needs permits. Los Angeles issues no-structural-change kitchen and bathroom remodels as express permits, and Chicago allows nonstructural remodels up to 2,000 square feet through its Express program.

Key Takeaways

  • Austin exempts painting, papering, tiling, carpeting, cabinets, countertops and similar finish work, but a new or replacement shower or tub is not exempt.
  • Nashville requires no permit for kitchen cabinets or vanities without electrical or plumbing in one- and two-family homes, but does for new shower or bath enclosures.
  • LADBS lists kitchen and bathroom remodels with no structural changes as express permits.
  • Chicago's Express program covers nonstructural remodels up to 2,000 square feet without moving walls, plus plumbing that adds up to 5 water supply fixture units.
  • Los Angeles issued 3,284 bathroom and 1,800 kitchen permits in 12 months.

Quick Facts

Los Angeles bathroom3,284 permits; median 22 days to issue
Los Angeles kitchen1,800 permits; median 30 days to issue
San Francisco bathroom1,940 permits; median 0 days to issue
Austin bathroom649 permits; median 70 days to issue
Chicago bathroom96 permits; median 20 days to issue

From our city pages and each city's open permit data (refreshed October 30, 2026).

Finish Work Versus Permit Work

Austin's published exemptions are typical. Painting, papering, tiling, carpeting, cabinets, countertops and similar finish work do not need a building permit for one- and two-family homes and townhouses up to three stories, and drywall repair up to 128 square feet is exempt unless it is part of a tub or shower surround. On the plumbing side, replacing fixtures, exposed traps, supply valves or faucets is exempt when no other departments or trade inspections are involved. But Austin says plainly that a new or replacement shower, tub, or tub and shower combination is not exempt.

Nashville's codes list reaches similar results for one- and two-family homes: no permit for kitchen cabinets (new, replacement or additional) or for vanities without electrical or plumbing, but a permit for new shower or bath enclosures and for relocating any electrical fixture, switch or outlet. The broader picture of what is exempt is in Work That Does Not Need a Building Permit: IRC R105.2 Exemptions.

Step-by-Step: What to Do

  1. List every element of the scope: finishes, fixtures, plumbing moves, circuits, walls, windows.
  2. Check each against your city's exemption list.
  3. If any item needs a permit, have the contractor pull the permit for the full scope.
  4. Schedule rough-in inspections before walls and floors are closed.
  5. Get the final inspection and keep the records.

Los Angeles: Remodels Without Structural Changes Are Express Permits

LADBS Information Bulletin P/GI 2026-003 lists "Kitchen/bathroom remodel for residential buildings (no structural changes)" as an express building permit, with no plan check. The same bulletin lists replacing and adding plumbing fixtures as express plumbing permits, replacing drywall (no new walls) in single-family homes and duplexes, and rewiring or adding devices to existing circuits as express electrical permits. Remodels that move bearing walls or add floor area go to plan check. The full express list is summarized in LADBS Express Permits for Re-Roofs and A/C Replacement.

Chicago: The 2,000 Square Foot Express Path

Chicago's Express Permit Program covers nonstructural residential remodeling up to 2,000 square feet without adding, removing or reconfiguring walls or doorways for rooms other than closets. With drawings by an Illinois-licensed architect or structural engineer, the same limit applies with wall changes. It also covers electrical work, mechanical work, and plumbing that adds up to 5 water supply fixture units; the city's own example is that adding a private bathroom is 4 units. Structural work, new stairs, converting unheated space to living space, and exterior work such as window replacement fall outside it.

San Francisco: Plumbing for Kitchen and Bath

San Francisco requires a permit before cutting into or replacing pipes, especially pipes that will be covered by a wall or buried. Plumbing work related to a kitchen or bath permit can be approved immediately for B-licensed general contractors on PermitSF, and separate permits are needed for plumbing and mechanical work. The city's data show how common these are: 1,940 permits; median 0 days to issue for bathrooms and 1,340 permits; median 1 days to issue for kitchens.

Remodel Permits Issued in the Last 12 Months

Bathrooms

CityMatching permits (12 months)Median days, application to issue
Los Angeles3,28422
San Francisco1,9400
Austin64970
New York26239
Chicago9620
New Orleans5728

Permits issued 2025-10-30 through 2026-10-30, matched by keywords in each city's published permit descriptions. A permit can cover more than one job, and description wording varies by city, so treat counts as a floor rather than an exact total.

Kitchens

CityMatching permits (12 months)Median days, application to issue
Los Angeles1,80030
San Francisco1,3401
Austin59477
New York6436.5
Chicago5823.5

Permits issued 2025-10-30 through 2026-10-30, matched by keywords in each city's published permit descriptions. A permit can cover more than one job, and description wording varies by city, so treat counts as a floor rather than an exact total.

San Francisco's near-zero medians reflect over-the-counter and express issuance. Austin's longer medians (70 days for bathrooms) show remodels there more often go through review.

What Usually Triggers the Permit in a Remodel

  • Replacing or adding a tub or shower, or building a new shower pan.
  • Moving a toilet, sink or drain, or adding any fixture.
  • New circuits, moving outlets or switches, or adding a bathroom fan.
  • Removing or adding walls, or enlarging a doorway or window.
  • Gas work for a range, or venting changes for a range hood.

If your scope has even one of these, ask for the permit to cover the whole job so inspectors see the rough-in before it is closed up.

Building Departments in the Cities We Cover

Rules in this guide vary by jurisdiction. These are the official departments that issue residential permits in the 15 cities we track, with the city's open-data source for permit records. Each city page shows the rules for roofing, HVAC, solar, fence and deck work.

CityIssuing departmentPermit records
Chicago, ILChicago Department of BuildingsChicago Building Permits
New York, NYNYC Department of BuildingsDOB NOW: Build – Approved Permits
Los Angeles, CALos Angeles Department of Building and Safety (LADBS)LADBS Building Permits Issued 2020–Present
Austin, TXCity of Austin Development Services DepartmentAustin Issued Construction Permits
Seattle, WASeattle Department of Construction and Inspections (SDCI)Seattle Building Permits
Orlando, FLCity of Orlando Permitting ServicesOrlando Permit Applications
Philadelphia, PAPhiladelphia Department of Licenses and Inspections (L&I)Philadelphia L&I Permits (Carto)
Baltimore, MDBaltimore City Department of Housing & Community Development (DHCD)Open Baltimore: DHCD Permits
Nashville, TNMetro Nashville Department of Codes and Building SafetyMetro Nashville Building Permits Issued
Raleigh, NCCity of Raleigh Permit and Development ServicesRaleigh Building Permits
San Francisco, CASan Francisco Department of Building Inspection (DBI)DataSF: Building Permits
New Orleans, LANew Orleans Department of Safety and PermitsNOLA Permits
Pittsburgh, PAPittsburgh Department of Permits, Licenses, and Inspections (PLI)WPRDC: PLI Permits
Cincinnati, OHCincinnati Department of Buildings & InspectionsCincinnati Building Permits
Kansas City, MOKansas City, MO City Planning & Development DepartmentKCMO Permits (CPD)

Before relying on any rule, read the department's current page or call its permit desk. Model-code sections cited here (such as IRC R105) are adopted locally, often with amendments.

Frequently Asked Questions

Do I need a permit to replace kitchen cabinets?

Usually not. Austin and Nashville both exempt cabinets for one- and two-family homes, provided no electrical or plumbing changes are involved.

Do I need a permit to replace a bathtub or shower?

In Austin, yes: a new or replacement shower or tub is not exempt. Nashville requires a permit for new shower or bath enclosures.

Is a bathroom remodel an express permit in Los Angeles?

Yes, if there are no structural changes. LADBS lists kitchen and bathroom remodels for residential buildings with no structural changes as express permits.

Can I add a bathroom in Chicago without plans?

Chicago's Express program allows plumbing that adds up to 5 water supply fixture units, and the city says a private bathroom is 4 units. Wall changes need drawings by an Illinois-licensed architect or structural engineer.

Written and maintained by the Home Permit Guide Editorial Team

Last updated

Every rule on this page links to the official source it was checked against. Read our Editorial Policy.

Sources

Official sources checked on . Rules change; confirm with the department before you start work.

  1. Austin DSD: Work Exempt from Building Permits (austintexas.gov)
  2. Metro Nashville Codes: Projects That May or May Not Require a Permit (filetransfer.nashville.gov)
  3. LADBS Information Bulletin P/GI 2026-003: Express Permits (No Plan Check Required) (dbs.lacity.gov)
  4. Chicago DOB: What Types of Work Are Eligible to Use the Express Permit Program? (chicago.gov)
  5. SF.gov: Apply for a Plumbing and Mechanical Permit (sf.gov)