Austin Building Permit Fees for Home Projects in 2026-27

Austin publishes its residential permit fees in one schedule, and the version for fiscal year 2026-27 took effect on October 1, 2026. Unlike Chicago, Austin's open data does not show what each applicant paid, so this guide sets out the official line items a homeowner is most likely to meet, and uses the City's permit records to show how often each kind of job comes through.

By the Home Permit Guide Editorial Team Updated Last checked 9 min read 4 official sources

Reviewed by Carlos Aldaba, CBO, Certified Building Official (ICC), Building Code & Permitting Consultant ·

Jump to the Answer
A white and brown wooden house among green trees
Photo: Unsplash. Illustrative only; it does not show a specific permitted project.

Short Answer

It depends on the route. A Residential Change-Out permit for replacing an HVAC system costs $74.05 for the first system and $20.69 for each additional one. A project that needs plan review starts with a $112.76 application processing fee, and an addition or remodel review starts at $197.23. New homes pay plan review from $986.15 plus separate building, electrical, mechanical, plumbing and energy permit fees.

Key Takeaways

  • Austin's FY 2026-27 residential fee schedule took effect on October 1, 2026 and was updated on October 14, 2026.
  • A Residential Change-Out permit for HVAC is $74.05 for the first system; the change-out program also covers water heaters, backflow devices, irrigation systems and water and sewer yard lines.
  • Plan review fees are paid at submittal and are non-refundable; permit fees are paid when the permit is issued.
  • Refunds, where allowed, equal 75% of the original permit less the minimum fee, and none are given once work or an inspection has happened.
  • Austin issued 3,002 water heater permits in 12 months, with a median of 4 days to issue.

Quick Facts

HVAC change-out (first system)$74.05; each additional system $20.69
Plan review application processing$112.76
Addition/remodel plan review, base$197.23
Small projects plan review$146.15 (fences, pools, garage conversions, porch enclosures)
Demolition permit$81.07 each, plus $60.50 pre-demolition inspection
Reinspection$83.85 per inspection

From our city pages and each city's open permit data (refreshed October 30, 2026).

How Austin Structures Residential Fees

Austin charges in layers. Projects that need plans pay a review fee when they are submitted, then permit fees for each trade when the permit is issued, then inspection-related fees if extra visits are needed. Simpler jobs use flat program fees instead. The City's fee schedule says the review fee is payable at submittal and is non-refundable unless collected in error, and the building and trade permit fees are payable at issuance.

Several departments contribute lines. Development Services sets most of them, but Austin Energy charges for new electric service applications and solar, Watershed Protection charges for floodplain reviews, and the Fire Department charges for wildland-urban interface and some residential fire reviews.

Every Project Type in Austin

These summaries come from the same official sources as our city pages and were last checked October 30, 2026. Permit counts are the city's own open-data records for the last 12 months.

Roofing: Often No

Austin exempts asphalt shingles that replace asphalt shingles, and any roof covering that does not affect the roof structure. You do need a permit (normally an Express permit) to replace more than 128 sq ft of roof decking, or if the home is in the Wildland-Urban Interface and 50% or more of the roof is replaced.

  • Exempt: like-for-like asphalt shingle replacement outside the WUI.
  • Permit required: more than 128 sq ft of roof decking.
  • Permit required in the WUI when 50% or more of the roofing is replaced.
  • Official fees: Express Residential Plan Review (FY2026): $136.45; Residential Express Permit (FY2026): $87.49.
  • Austin issued 485 matching permits in the last 12 months, with a median of 4 days from application to issue.

Source: Austin DSD: Work Exempt from Building Permits · Full details: Do You Need a Roofing Permit in Austin?

HVAC: Yes

Replacing a central heat and air system, a packaged unit or a mini-split in a one- or two-family home requires a Residential Change-Out permit, pulled by a licensed mechanical contractor. Replacing supply and return duct runs alone is exempt.

  • HVAC replacement uses the Residential Change-Out permit (Residential Code R109.5).
  • The responsible contractor must be a licensed mechanical contractor.
  • Exempt: replacing supply/return duct runs and minor parts.
  • Austin issued 1,891 matching permits in the last 12 months, with a median of 4 days from application to issue.

Source: Austin Build + Connect Manual: Change Out Permits · Full details: Do You Need an HVAC Permit in Austin?

Solar Panel: Yes

Solar panels or solar shingles inside Austin city limits that interconnect to Austin Energy need a residential building permit. Systems in the ETJ use a separate auxiliary permit through the AB+C portal.

  • Inside city limits: residential building permit.
  • In the ETJ: separate solar permit through the AB+C portal.
  • Interconnection with Austin Energy is part of the process.
  • Austin issued 621 matching permits in the last 12 months, with a median of 8 days from application to issue.

Source: Austin DSD: Types of Permits · Full details: Do You Need a Solar Panel Permit in Austin?

Fence: Usually No

A fence up to 7 feet high is exempt from a building permit unless it is in a flood hazard area. A permit is required above 7 feet, and residential fences over 6 feet along a public right-of-way also need a letter of authorization.

  • Exempt: fences up to 7 ft outside a flood hazard area.
  • Permit: any fence in a floodplain or over 7 ft.
  • Over 6 ft along a public right-of-way needs a City letter of authorization.
  • Austin issued 52 matching permits in the last 12 months, with a median of 72 days from application to issue.

Source: Austin DSD: Fencing Regulations · Full details: Do You Need a Fence Permit in Austin?

Deck: Usually Yes

A deck is exempt only if it is 200 sq ft or less, no more than 30 inches above grade, not attached to the house, not used for egress and not in a flood hazard area. Other decks need a building permit; repairs limited to existing deck boards are exempt.

  • Exempt: detached decks up to 200 sq ft and 30 in above grade.
  • Exempt: non-structural repairs limited to deck boards.
  • Attached decks need a building permit.
  • Austin issued 274 matching permits in the last 12 months, with a median of 101 days from application to issue.

Source: Austin DSD: Work Exempt from Building Permits (linked above) · Full details: Do You Need a Deck Permit in Austin?

ProjectPermit needed?Permits (12 mo)Median days to issue
roofingOften no4854
HVACYes1,8914
solar panelYes6218
fenceUsually no5272
deckUsually yes274101

Step-by-Step: What to Do

  1. Find out whether the job is exempt, a change-out, an express permit or a plan-review project.
  2. For plan review, budget for the $112.76 application processing fee, which is paid at submittal and is non-refundable.
  3. Add the review tier for your project size and the permit fees that are paid when the permit is issued.
  4. Allow for reinspections at $83.85 each if work is not ready when the inspector arrives.
  5. Check whether tree, floodplain or fire review applies, since those add separate fees.

Plan Review Fees for Additions, Remodels and New Homes

Review typeFY 2026-27 fee
Application processing fee$112.76
Express residential plan review$112.76
Small projects plan review (garage conversions, carport or porch enclosures, amnesty CO, fences, pools)$146.15, plus $146.15 per additional small project
Addition or initial remodel, base fee (up to 100 sq ft)$197.23
Addition or remodel, 101 to 200 sq ft$394.46 plus a per-square-foot charge
Addition or remodel, 401 to 500 sq ft$986.15 plus a per-square-foot charge
New construction, base fee$986.15
New construction, 2,001 to 3,000 sq ft$1,380.61 plus a per-square-foot charge
Resubmittal or major plan revision$585.77
Minor plan revision$92.57

A major revision is one that needs revised plans or changes calculations; a minor revision is administrative. Projects that need engineering review pay more: grading and drainage review is $386.63 at the preliminary stage and $1,031.02 for full plan review, and a detailed floodplain review from Watershed Protection is $470.

Permit Fees When the Permit Is Issued

For single-family homes, duplexes, townhouses and other residential structures, each trade has its own base fee, which then rises with floor area above 1,000 square feet:

TradeBase fee
Building$318.48
Plumbing$220.47
Electrical$183.69
Mechanical$127.68
Energy$72.38

Added together, the base fees come to $922.70 before any floor-area charges, review fees or other departments' lines. That is why a new home or large addition in Austin often costs several thousand dollars in total, while a single replacement job costs under $100.

Flat Fees for Common Home Jobs

ItemFY 2026-27 fee
Residential Change-Out permit, HVAC (first system)$74.05
Each additional HVAC system$20.69
Residential express permits and kitchen remodels, inspection$72.96
Inspections for standalone projects$73.81; $28.01 per inspection after two
Demolition permit$81.07 each
Pre-demolition inspection$60.50 each
Demolition or relocation processing fee$106.72
Residential roof replacement inspection (Fire)$370.00
Solar permitting intake fee$53.56, plus Austin Energy's $169.83 auxiliary power base fee and an $84.92 inspection fee for 1 to 50 kW

The schedule notes that the change-out program also covers water heaters, replacement of backflow devices, irrigation systems, and water and sewer yard lines. The rules on who qualifies are explained in Austin's Residential Change-Out Permit for HVAC. The Fire Department's roof replacement inspection and wildland-urban interface fees apply case by case, depending on the property.

How Busy Austin's Permit Office Is

We matched keywords in permit descriptions from Austin's open data for permits issued from October 30, 2025 to October 29, 2026. The counts show where the flat-fee routes do their work:

ProjectMatching permitsMedian days to issue
Water heater3,0024
Electrical panel or service1,6245
Windows1,31020
Siding65626
Demolition64333
Bathroom remodel64970
Kitchen remodel59477
Accessory dwelling unit83164

Water heaters and panel work, which usually go through fast routes, were issued in a median of a few days. Kitchen and bathroom remodels, which often need review, took a median of more than two months, and accessory dwelling units took longest. Time matters as much as fees here, because each failed or incomplete inspection adds an $83.85 reinspection fee.

Refunds and Other Charges to Know

  • No refund is given once work under the permit has started, once an inspection has been performed, scheduled or requested, or if only the minimum fee was paid.
  • Where a refund is allowed, it equals 75% of the original permit fee less the minimum fee for that permit type, and it must be requested in writing with the receipt.
  • An expired permit costs a contractor $53.56 per permit, and a permit maintenance fee is also $53.56.
  • General contractor registration is $82.56, but the schedule says it does not apply to people acting as contractors on their own homestead and principal residence.
  • After-hours inspections are $166.57 per hour, with a one-hour minimum.

For how permit fees compare across cities and what else belongs in a project budget, see How Much Does a Building Permit Cost? Verified Fee Examples.

Where to Go Next

For Austin's rules on specific projects and live permit counts, start at Austin Building Permits for Home Projects.

Who Issues Permits in Austin

Residential permits in Austin are issued by the City of Austin Development Services Department. Its website has the current application portal, fee schedule and inspection scheduling. Issued permits are published as open data in Austin Issued Construction Permits, which is the source of the permit counts and recent permits shown on our Austin pages. Rules and fees change, so confirm with the department before you start work.

Frequently Asked Questions

How much is a building permit in Austin?

It depends on the project. An HVAC change-out permit is $74.05 for the first system. Plan-review projects start with a $112.76 application processing fee, and an addition or remodel review starts at $197.23, before permit and inspection fees.

When did Austin's current permit fees take effect?

The FY 2026-27 residential fee schedule took effect on October 1, 2026, and the City updated it on October 14, 2026.

How much is a demolition permit in Austin?

The demolition permit is $81.07, the pre-demolition inspection is $60.50, and the demolition or relocation processing fee is $106.72. Tree review and inspection fees can also apply.

Are Austin permit fees refundable?

Plan review fees are non-refundable unless collected in error. Permit fee refunds equal 75% of the original fee less the minimum fee, and none are given after work or an inspection has taken place.

How much is a reinspection in Austin?

A reinspection costs $83.85 each time an inspection has to be repeated because work was incomplete, earlier corrections were not made or the site was not accessible.

Written and maintained by the Home Permit Guide Editorial Team

Last updated

Every rule on this page links to the official source it was checked against. Read our Editorial Policy.

Sources

Official sources checked on . Rules change; confirm with the department before you start work.

  1. City of Austin: Residential Building Plan Review & Inspection Permit Fees (Effective 10/01/2026) (austin.widen.net)
  2. Austin Development Services: Fees (austintexas.gov)